2EG ESD system Revamp at SHARQ/SABIC
2EG ESD system Revamp at SHARQ/SABIC
2EG ESD system Revamp at SHARQ/SABIC:
- Invensys Triconex ESD System
- Massive amount of Demolition
- Replacement of Existing ESD System
Installation:
- Installation work conducted during short Shutdown Period.
Project Time
- Twenty Eight (28) cabinets replaced during 10 days shutdown period
Planning was done:
- Appropriate Planning was done
- All procurement made timely
- Pre-Shutdown period has been well utilize
- All activities that could be done during pre-shutdown has been completed